Cable Trough Grangemouth Substation

At Grangemouth Substation the team at MCS were tasked with installing 50m 132kv ducting, 3 triform and jointing bay in this cable trough. Below are some examples of the steps we had taken to installing and reinstating.

As seen in picture we came across many services. Trial holes and safe digging were key to avoid any strikes.
Correct spacing and sand along with stock bored marker tiles.
Correctly battered for easy access and egress.
Prepping jointing bay for jointers.
132kv cables install.
Marker tapped.
Ground backfilled and levelled.